Project: I-CAVS   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:paolo cavosi   -  
Project:   Vans - RV-10
Total Hours:2429.2
Total Flight Time:
Start/Last Date:May 28, 2019 - No Finish Date
Engine:IO-540 Thunderbolt Serial # EL-38135-48E
Propeller:MT Propeller MTV-12-B/193-53 serial 22G1268-K
Panel:Garmin G3X
 
Friendly URL: https://eaabuilderslog.org?s=I-CAVS

Home or Last Project Picture

May 23, 2020     7-11 Rudder Step 1-6 trailing edge back riveting - leading edge roll - (5 hours) Category: Tail Feathers
after several weeks after applying the tank sealant to the trailing edge i removed the clecos, cleaned all the excess and cleaned the holes for the rivets.
With help of Lucio i backriveted the trailing edge obtaining a very straight edge with a limited bulge to an excess of sealant i didn't squeeze away properly. In general the result is very good.
After that we prepared the rolling of the leading edge making sure the rudder was laying flat and using a 1"" aluminium pipe. We didn't bend the edges as suggested, however the result is very good.
Final activities were dedicated to the counterbalance weight positioning, match drilling and final bending of the skins. We resolved to avoid placing a rivet in the middle of the two screws and placing instead a screw with the corresponding K-1000-08 nut plate.
 